Get to know the quantities behind your design

A bill of quantities gives you another way to understand a home concept: what the model contains, what has been estimated from it, and which items still need more information. Use it to prepare a clearer conversation with your designer or quantity surveyor.

The report provides indicative quantities only. It is not a cost estimate: it contains no prices or rates, and it is not a tender document.

Choose the design and download

Open the scene you want to review. In Export, find Quantities and choose bill (.txt, indicative) for a readable summary or bill (.csv, every row) for the detailed table. These two downloads use the current scene, including manual edits.

During a generation conversation, the Quantities button reads that generated turn instead. Later hand edits are outside that report. Opening a report or downloading quantities uses no generation allowance.

Choose the regional practice

The site practice setting controls material assumptions, such as brick sizes and mixes. It is separate from the m or ft setting you use to read the design. Choose American, Australian, European, Indian, Pakistani, Gulf, or Turkish in the Export menu, or leave it on Automatic.

Understand Automatic

An explicit selection takes priority. Otherwise, ChatHome.ai uses the country named in the generated brief when it maps to a supported practice, then the region on your account, then American. The report names the practice and explains where the choice came from.

You can choose an optional account region at signup or change it later by opening your account from the email control. A practice selected in Export is remembered in that browser and continues to override Automatic until you change it.

Choosing a practice changes the materials summary and its assumptions; it does not redesign the house or establish local code compliance.

Read quantities in familiar units

The text summary always includes metric figures. When the studio is set to ft, it also shows feet, square feet, and cubic feet equivalents under any regional practice. American and Pakistani practices already include these equivalents when the screen is set to m.

These are rounded conversions of the same quantities. Switching units does not change the chosen practice, material assumptions, or house. The quantities CSV and change log remain metric. Compare units across the editor and downloads.

If you opened Quantities in chat

That report keeps the units used when you requested it. Changing m or ft later does not rewrite an existing report bubble. Request Quantities again to see it in your new choice.

Read three kinds of information

Measurements from the model

Look for walls and their openings, floor and roof areas, door and window schedules, and room finishes. Where the model contains a frame, the report includes its concrete quantities and member schedules. Fixtures are counted from the pieces actually placed.

Quantities based on assumptions

Some quantities need information beyond the visible shape. Slab volumes use an assumed thickness; plaster and screed use stated depths. Strip footings, pad footings, and lintels draw on the preliminary structure report. Their assumed loads and ground-bearing value have no code basis.

Reinforcement uses a disclosed ratio for each element, never a bar-bending schedule. These figures, foundation sizes, and material references need professional checking and project-specific specifications.

Allowances that still need detail

Read the allowances separately from measured quantities. An allowance identifies work the model has not measured; it is not a quantity of zero. Keep these open items with your project questions.

Use the CSV for a closer review

The CSV lists the item number, section, item, quantity, unit, wastage, quantity with wastage, specification, and note. It also contains the per-room finish schedule. Check the unit and the explanation beside a figure before comparing it with another row.

The download header identifies the design, generation, revision, date, and practice where that information is available. A hand-drawn scene can still produce quantities without a stored generation. Save the matching JSON and PDF alongside the report so the recipient knows which concept it describes.

Compare quantities after a revision

For a generated revision with an available parent, Export offers a quantities change log. It compares that stored revision with the previous one using the same practice for both. Unsaved edits are not in it, and later manual edits to a cloud design are not generated revisions either.

For example, after enlarging a kitchen, review which quantities increased, decreased, appeared, or disappeared. A result rebuilt under an updated model can include differences beyond your request; the log identifies that situation.

The change log helps explain two stored results. Keep separate design copies when you want to preserve alternatives you can reopen and edit.

Bring the figures into the next conversation

Share the summary, detailed CSV, matching design, and your open questions. Ask the recipient to review the assumptions and allowances against the actual project before using the quantities for construction decisions.

Read the preliminary structure report.

Keep and compare design alternatives.

Share a model with your designer.

Try it with your own design

Open the studio

Back to Export options.